New Milestone in Bullet train project: Viaduct Installation over 25km completed. pic.twitter.com/Ayl4OoJfx3
— Ministry of Railways (@RailMinIndia) January 17, 2023
Bullet Train Progress (as on 31.12.22):
Overall Physical Progress: 24.73%
Gujarat: 30.68%
Maharashtra: 13.37%– Pile work: 227.62 km
– Pier work: 126.44 km
– 21.44 km Girders launched
– First Rail Level slabs of 50 m each at Surat and Anand stations have been cast pic.twitter.com/p3NPz9Hptf— Ministry of Railways (@RailMinIndia) January 11, 2023